What We Could Have Done Better: Lessons from the Franconia Ridge Loop Restoration

Nathaniel Scrimshaw

This is the third in a four-part series reflecting on the accomplishments of the Franconia Ridge Loop Restoration, what we could have done better, and where we go from here.

View of the “Lincoln Scrambles South,” Mount Lincoln and Mount Lafayette, on Franconia Ridge.

In the previous article, I discussed some of the things we got right in the Franconia Ridge Loop Restoration: trail realignment, reverse-grade drainage, carefully designed step clusters, foundation steps, full-bench construction, proper tread preparation, and trail widths appropriate for very high levels of use.

Together, these represented an important advance toward a new standard for sustainable trail construction in the White Mountains.

But we did not apply that standard consistently. Understanding why is important, not to diminish what has been accomplished, but because the lessons from this project should inform how we plan the next generation of major trail projects.

An Ambitious Goal Without a Complete Plan

We should begin by acknowledging that the original goal of the project, to “redesign the Franconia Ridge Loop from start to finish,” proved overly ambitious given the available funding and the actual condition and use level of the trail.

As mentioned in the first article in this series, five years later, substantial work remains even on the two major approach trails, Old Bridle Path and Falling Waters Trail. Only a relatively small amount of work has been completed on the upper Greenleaf Trail in the alpine zone. And no congressionally funded restoration work was undertaken on perhaps the most ecologically sensitive portion of the entire Loop: the Franconia Ridge Trail between Mount Lafayette and Little Haystack.

Part of the problem was built into the project from the beginning.

The  $1.125 million in Congressionally Directed Funding was not the result of a detailed assessment of every section of the Loop followed by engineering and trail-design estimates of what it would cost to rebuild it. Rather, it represented the level of funding that could be secured through the congressional appropriations process.

That is understandable. Nothing comparable had previously been attempted on this scale in the White Mountains, and more than a million dollars sounded like an enormous investment in a single trail system.

And it was an enormous investment. It just wasn’t enough to accomplish the stated goal.

The Missing Variable: Use

One reason the cost was underestimated was that we had not fully incorporated the extraordinary volume of use on the Franconia Ridge Loop into our understanding of what reconstruction would require.

Today the Loop receives approximately 45,000–50,000 visitors between May and October. That changes almost everything about trail design.

A technique that might perform adequately on a trail receiving a few thousand hikers annually can deteriorate rapidly when thousands of boots pass over it in a matter of weeks. A narrow tread that works perfectly well elsewhere can result in hikers continually stepping around one another. Organic soil that might gradually compact and harden on a lightly traveled trail can quickly erode and expose roots and rocks.. A drainage feature requiring regular cleaning becomes a significant liability if the maintenance system cannot reliably provide that cleaning.

Add increasingly intense rain events, and the engineering challenge becomes greater still.

This had a cascading effect on the project. As it became apparent that the available money would not rebuild the entire Loop to the standards we had envisioned, choices had to be made about how far the money could stretch.

There was another structural problem as well. The congressional funding applied to the portions of the Loop on federal land, leaving significant sections of the Old Bridle Path and Falling Waters Trail within Franconia Notch State Park outside the federally funded project.

WTN Americas was ultimately able to secure private funding, later supplemented by a New Hampshire Recreational Trails Program grant, to begin filling that gap. But ideally the Loop would have been conceived, assessed, designed and funded from the beginning as one trail system crossing two jurisdictions.

Peter Jensen, Peter Jensen & Associates LLC and rocks steps constructed to the original standard we agreed to.

We Established Standards, Then Lost the Mechanism for Maintaining Them

There was an important effort at the beginning of the project to address precisely these questions.

The Partnership to Restore the Franconia Ridge Loop formed a trail standards working group during the first year. That group brought people together to establish many of the design and construction principles discussed in the previous article.

That was exactly the right idea.

Unfortunately, the working group stopped meeting.

Without a continuing mechanism for reviewing design, comparing work among different crews, documenting what was being learned, and adjusting standards as the project progressed, some of those standards were applied inconsistently.

Four examples stand out.

Trail Width

One was tread width.

Early in the project, we recognized that a trail carrying tens of thousands of hikers must be wide enough to accommodate actual visitor behavior, including people passing one another without continually stepping off the constructed surface.

As costs increased, however, reducing tread width offered an obvious way to make limited funding cover more trail.

In some places, I believe this went too far.

There are reconstructed sections where the tread is narrow enough that hikers meeting one another are likely to step outside it. At Franconia Ridge levels of use, thousands of seemingly insignificant passing movements can eventually widen the trail anyway, except that the widening occurs through trampling and erosion rather than intentional construction.

This illustrates one of the central lessons of the project: Reducing the dimensions of a trail does not necessarily reduce its ecological footprint.

Sometimes spending more to construct a wider, durable tread is precisely what allows us to keep people within a smaller overall corridor.

Trail eroding/compacting below steps constructed in 2024, below foundation steps.

Foundation Steps

Foundation steps were another standard applied inconsistently.

As discussed in the previous article, a properly placed foundation stone at the base of a stair cluster protects the staircase from being undermined as water and foot traffic remove soil below it.

For some crews, this represented a different approach from their previous stonework practices. It also requires another substantial piece of stone and additional labor. Under the pressure of time and budgets, that additional work can seem expendable.

It isn’t.

Where a staircase is undermined from below, the effective height of the bottom step increases and the stability of the staircase above can eventually be compromised.

We are also discovering something we did not fully anticipate. In some locations, foundation stones that were originally flush with the tread, or even slightly buried, are now protruding two to four inches after only a few years as surrounding tread material erodes.

If that continues, a foundation stone intended to protect a staircase can eventually become a step itself, but a step with no foundation stone beneath it.

That tells us something important. Even some of our improved construction techniques need to be monitored over time and modified in response to what actually happens on a trail receiving this intensity of use.

Waterbars Versus Reverse Grade Drainage

We also did not consistently make the transition from traditional waterbars to drainage created through trail alignment and grade reversals.

Some newly reconstructed sections still rely on waterbars. Several are already beginning to collect sediment and debris.

The problem is not that waterbars never work. They do. The problem is that their effectiveness depends upon maintenance.

And this exposes a larger contradiction in White Mountain trail management: we continue to build drainage structures that depend upon a level of routine maintenance we often do not have the capacity to provide.

Where terrain allows, reverse grades and appropriately shaped tread offer a fundamentally different approach. Instead of asking someone to repeatedly restore the drainage, we build drainage into the geometry of the trail itself.

That distinction becomes increasingly important as rainfall becomes more intense and maintenance needs increase.

What Lies Beneath the Tread

Perhaps the issue that concerns me most as the federally funded phase of the project concludes is tread preparation.

In some sections we underestimated the depth of the organic soil beneath the existing trail.

On a lightly used trail, it may sometimes be possible to allow a new tread to evolve gradually. Organic material compacts or erodes, rocks and roots emerge, and crews return periodically to improve the surface as the trail hardens.

Franconia Ridge doesn’t provide that luxury.

Thousands of hikers can pass over a newly reconstructed section in a matter of weeks. If unsuitable organic material remains beneath the tread, deterioration that might take years elsewhere can happen in months.

During these final weeks of the project, there is understandable pressure to finish as much trail as possible. In some places, that has meant leaving more organic material in the tread than I believe is desirable.

With careful monitoring and rapid intervention as problems emerge, it may be possible to progressively harden these sections. But that requires professional trail crews to return when problems first appear, rather than years later after deterioration has become severe.

In that sense, we are conducting an unplanned experiment in adaptive trail management.

The experiment may work.

But only if somebody is there to observe the results and has the resources to respond.

And What About All Those Steps?

There is an even larger design question worth asking.

As I described in the previous article, one of our White Mountain compromises has been to alternate lower-grade side-hill trail with relatively short clusters of stone steps. This allows us to gain elevation within constrained terrain while avoiding a continuously steep trail.

I continue to believe this can be an effective approach.

But a trail designer looking at the Franconia Ridge project from outside the White Mountains might reasonably ask:

Are we still building too many steps?

Stone staircases are expensive to construct. Hikers sometimes bypass them. They concentrate elevation gain into short distances. And unless drainage is carefully incorporated into their design, water can accelerate down them and erode the tread below.

The question should not be whether steps are good or bad. It should be whether we have found the right balance between steps, climbing turns, longer contour alignments, grade reversals and other ways of gaining elevation.

Above Treeline Is a Different Trail Problem

There was another fundamental issue that the original project planning did not adequately address: the Franconia Ridge Loop is not one trail environment.

Much of what we have discussed so far applies primarily to trails below treeline. There we can realign trails across forested slopes, excavate full-bench tread, mine mineral soil, build cribbing, construct grade reversals and, where appropriate, move the trail substantially away from its historic alignment.

Above treeline, we enter a fundamentally different ecological and management context.

On the Franconia Ridge Trail between Mount Lafayette and Little Haystack, the trail passes directly through a small and exceptionally vulnerable alpine ecosystem. Soil is thin, vegetation grows slowly, opportunities for realignment are limited, and even relatively small amounts of trampling can expand the disturbed corridor.

At the same time, this is where visitor behavior becomes particularly important.

Traditional scree walls have long been used to define the trail corridor above treeline, but at Franconia Ridge levels of use they are often inadequate by themselves. People step over them, walk around other hikers, leave the tread at viewpoints, and create parallel paths around high steps and other pinch points.

The appropriate response therefore cannot simply be more stonework.

Alpine trail management needs to combine physical trail design with active management of visitor movement. That can include appropriately wide and clearly defined tread, elimination or reconstruction of high steps and pinch points, strategically located pull-outs and passing areas, cairns and other route-definition techniques, temporary string fencing, interpretive signage, restoration of unnecessary parallel tread, and the visible presence of Summit Stewards who can both educate visitors and respond to emerging problems.

In other words, above treeline the distinction between trail construction and trail stewardship begins to disappear.

A trail crew can rebuild a section of tread. But whether hikers remain on that tread depends upon its width, the height and placement of its steps, where people naturally stop and pass, how clearly the route is defined, what visitors understand about the vegetation around them, and whether somebody is present to observe how the system is actually functioning.

The congressionally funded project never substantially reached the Franconia Ridge Trail beyond Mount Lafayette.

In retrospect, that may have been fortunate.

Simply extending the below-treeline construction model across the ridge would not have been enough. The alpine section requires its own assessment, design standards, visitor-flow analysis and management plan before major reconstruction begins.

WTN Americas Summit Stewards have already undertaken substantial trail tending and restoration work on Franconia Ridge, giving us an opportunity to experiment with some of these approaches on the ground. Building on that experience, the Alpine Stewardship Center has proposed a new model of integrated alpine trail management in which Summit Stewards are trained not only in visitor education and ecological stewardship, but also in increasingly advanced trail work. Stewardship, monitoring, trail reconstruction and adaptive management become parts of the same job rather than separate activities carried out by different programs.

That may point toward something larger than a solution for Franconia Ridge.

It may provide a model for how we manage heavily visited alpine trails throughout the White Mountains.

WTN Americas Summit Stewards on the summit of Mount Lafayette.

The Larger Lesson

None of these shortcomings negate the accomplishments of the Partnership to Restore the Franconia Ridge Loop.

Quite the opposite. We now know much more than we did five years ago.

But perhaps the most important lesson is that the next project of this scale should begin differently.

Before announcing that we will rebuild a trail from start to finish, we should conduct a detailed trail log and condition assessment. We should document visitor volumes and behavior. We should identify the different ecological and management environments through which the trail passes rather than assume that one design approach applies everywhere. We should divide the trail into management and construction units, identify the appropriate treatment for each, establish construction standards, estimate costs from those designs, and then determine the funding and timeframe required.

And the standards group should not disappear once construction begins.

It should become a standing design and technical review team that walks completed work, compares approaches among crews, monitors failures and successes, and updates standards throughout the life of the project.

Most importantly, we should stop thinking of a major trail restoration as something that is finished when the construction grant ends.

A trail carrying 45,000–50,000 visitors through steep mountain terrain, including an extraordinarily sensitive alpine ecosystem, requires continuing professional attention: monitoring, maintenance, reconstruction, ecological stewardship, visitor management and adaptation.

And that brings us to a conclusion I did not fully appreciate when the Franconia Ridge project began five years ago.

The challenge facing Franconia Ridge is not simply that we have deteriorated trails that need to be rebuilt.

We have a trail management system that needs to be rebuilt as well.

For much of the last century, the White Mountains have depended upon an extraordinary patchwork of federal and state agencies, nonprofit organizations, professional trail crews, seasonal programs, trail adopters and volunteers. That system has accomplished remarkable things. But it was largely created for another era of recreational use, another level of funding, and another climate.

Franconia Ridge is showing us the limits of that system.

It is also showing us pieces of what might replace it: trails designed for actual visitor volumes; professional construction integrated with volunteer work; permanent technical review and monitoring; Summit Stewards who combine visitor management with trail tending; and adaptive management that responds to what happens on the ground rather than waiting decades for the next major reconstruction project.

That is a much larger subject than the Franconia Ridge Loop Restoration.

Next in this series: The White Mountains Trail Management Crisis, and What Comes Next.